NHPC plans to start commissioning 3 units (250 MW each) of the 2,000 MW Subansiri Lower Hydroelectric Project in June 2025, pending approval from the National Dam Safety Authority. The remaining 5 units are expected by May 2026. The project is India’s largest hydroelectric venture.