Train to Manipur: Indian Railways shares progress report of Jiribam-Imphal rail project
The progress report Jiribam-Imphal rail project. 89.2% of work on the train to Manipur project is now complete. Indian railways have finished the work on 48 out of 52 tunnels and construction of 6 out of 11 stations is also complete. Of the 11 major bridges, the substructure of 7 and superstructure of 5 have been completed while 101 of 129 minor bridges are also ready.
The work on the world’s tallest railway pier bridge in Manipur is also going on in full swing.
Jiribam-Imphal, Manipur Project Progress Report:
1) 89.20% of work completed
2) Tunnels- 48 of 52 completed
3) Bridges:
– Major: 11; substructure of 7
and superstructure of 5 completed
– Minor: 101 of 129 completed
4) Stations: 6 of 11 constructed pic.twitter.com/S2WYYi2HrG— Ministry of Railways (@RailMinIndia) August 20, 2022