Train to Manipur: Indian Railways shares progress report of Jiribam-Imphal rail project

The progress report Jiribam-Imphal rail project. 89.2% of work on the train to Manipur project is now complete. Indian railways have finished the work on 48 out of 52 tunnels and construction of 6 out of 11 stations is also complete. Of the 11 major bridges, the substructure of 7 and superstructure of 5 have been completed while 101 of 129 minor bridges are also ready.

The work on the world’s tallest railway pier bridge in Manipur is also going on in full swing.